AWARE-Ontario.ca

 

CBM St. Mary’s Cement Inc., Bishopsgate Road, Burford

 

Comment on Environmental Registry (EBR 011-7914) until February 18, 2013.

 

 

Comment suggestions by the Concerned Citizens of Brant:

 

Re: EBR Registry Number: 011-7914 – CBM pit on Bishopsgate Rd.

 

A great deal of effort has been put into these comments. Please do not disregard them, do not ignore them. These issues will be required to be addressed before any new licences are granted in the County of Brant. The people of Brant stand ready to protect our water, our health and our future.

 

My name is <name> & I support this submission by CCOB. I am a Concerned Citizen Of Brant!

 

According to the hydrogeological assessment of the Olszowka property, section 5.2.4 talks about the temperature of the groundwater and indicates that groundwater above 5 meters is subjected to 4-12 degree variations however water below 7 meters stays relatively stable. Removing the 5-7 meters of earth will also expose the aquifer to within 1 meter or less of the surface and will heat the water table under the entire operation by as much as 10 degrees. This calculation was not included when determining potential effects on the natural wetland areas.

 

This increase in temperature was noted in the same study that the thermal plume data was based on; “Thermal Plume Transport from Sand and Gravel Pits – Potential Thermal Impacts on Cool Water Streams ” (Jeff M. Markle and Robert A. Schincariol, February 2007)

 

They say this in their abstract:  “The annual temperature amplitude in the pit is 10ºC above up gradient ground water, and our results show that alternating warm and cool plumes persist in the aquifer for 11 months and migrate up to 250 m down gradient.”

 

The CBM information stated above explains and verifies the 10ºC difference noted in the thermal plume study. There is no calculation for the new increased groundwater temperature based on the new elevation of the pit floor and the thermal plumes that emanate from the pit itself.

 

Also important to note is that the “terms of reference” of this study was the thermal plumes only emanating from the pond and not the overall increase in temperature created by the pit as it has been utilized for in this report. The thermal plume study pit was already excavated and so it could not have allowed for the overall increase of 10 degrees as it was only noted in their abstract. The temperature readings for the creek used in the study were already elevated from the effects of the pit itself.

 

The thermal plume study also said the following in their recommendations:  “This study demonstrated that aggregate extraction can impact stream temperatures if sufficient separation distances are not provided, and that these temperature changes may adversely affect the macroinvertebrate community and incumbent brook trout populations. The cumulative effects of several operations within the watershed are still unknown. Quantifying these effects will require a highly integrated study so that we may understand the ground water – surface water interaction within the watershed and the links to the ecology in the context of the stream environment.”

 

They themselves are calling for more intensive studies and cumulative impacts studies as well. None of these recommendations have been followed. There appears not to be any studies that verify these results. Considering the number of aggregate extractions in wetland areas, and the ease of monitoring temperature, there is absolutely no acceptable excuse to not have carried out this “intensive” study.

 

A cumulative impact study has been requested for quite some time from many different groups. The opportunity to have this completed by now was there so the lack of this study is the fault of the industry. Until this issue is addressed and the actual effects of an aggregate extraction are studied, no new pits should be approved.

 

In the CBM study, it was said:  “The thermal assessment is based on the understanding that the pond water would be subject to the influence of ambient air temperatures throughout the year, and that this will affect the temperature of the water migrating through and exiting through the extracted pond”. There was never any mention of the 10 degree increase caused by the extraction itself and therefore, is not included in any of the projections. This means that all temperature projections could be out as much as 10 degrees. This is unknown because it has not been measured. An increase in groundwater temperature has been calculated only using the theory that the water is heated as it filters through the ponds (thermal plumes).

 

According to “Thermal Plume Transport from Sand and Gravel Pits – Potential Thermal Impacts on Cool Water Streams ” (Jeff M. Markle and Robert A. Schincariol, February 2007), thermal plumes extend 250 meters however 120 meters was used. The explanation is based on an “assumed” travel time of .2m/day. Many assumptions are made to create this calculation and it should be noted that this data was based on 1 study.

 

The CBM report explains that “hydrogeological investigations and groundwater modelling are dynamic and inexact science” & The validity & accuracy of the model depends on the amount of data available relative to the degree of complexity of the geologic formations, the site geochemistry…” ending with “no warranty, expressed or implied, is made” and it is made clear that they are not accountable if they are wrong.

 

According to a publication released by the Canadian Environmental Law Association – Aggregate Extraction in Ontario: A Strategy for the Future:  “In the case of aggregate operations that extend below the water table, a number of negative hydrological impacts may occur. During the process of dredging an aggregate pit, gravel that is removed may be replaced with groundwater and precipitation, and evaporation from on-site ponds can occur at a faster rate than would occur from the natural land surface. Levelling out of the groundwater table in the pit pond can also cause alteration of groundwater flow patterns in surrounding areas.”

 

“Lowering of the water table during aggregate extraction may drain surrounding wetlands that are fed by groundwater discharge.”

 

Why is it that these hydrogeological studies have never been re-evaluated after the projects were completed and used to verify the integrity of their data and predictions? Considering the weight these studies have been given, you would think that the science that backs them would be solid however there is no science and the company will not back their own predictions. Witnesses state that wetlands are frequently destroyed however this information is ignored. The verification and feedback system that is used to perfect any science or process is completely missing. The predictions in the study are therefore invalid. Until the science has been proven and backed by those presenting it, it should all be inadmissible to support the case.

 

“Closed loop washing system”

 

“Closed loop” suggests that the wash system is somehow not connected to the environment however this is far from the truth. The wash ponds are just holes in the aquifer and the settling ponds are also just big holes. There is no prevention of the wash water, or any contaminants released through the washing process, re-entering the environment from many access points including ponds and stacks of washed materials.

 

The water loss of 3% due to “industry experience” sounds like a guess. “Virtual water trade” estimates the actual water loss for many products however I have been unable to locate any studies on aggregates. Please provide this data or it must be considered a “guess”. There is no room for guessing in science and should not be presented as science. I have seen no calculations for water loss due to water atomization for example. 3%?

 

A dust mitigation plan includes the application of water to haul routes. How much water will this use? Will there be any chemicals added to the water? Will this water be allowed to drain back into the aquifer? Has this been shown in the water loss calculations?

 

Last year’s drought showed us that the Provincial government has no interest in protecting our quantity of water. This can be verified in the Environmental Commissioner’s report. The GRCA has the science that shows that the drought conditions will only get worse. They predict a battle over water. Please consider the “State Of Climate Change” report by the GRCA.

 

The CBM report says that Landon’s Creek & the West Tributary is a result of precipitation, snow melt groundwater and runoff. With the elevation of the land around the wetland area being reduced to a lower level, this would eliminate runoff as a source for these natural areas.

As well, it is said that these lake will increase the volume of water that an aquifer can hold. That also means that they will displace a lot of water and potentially lower the water table. Lowering the aquifer will effect the ability of the wetlands to be fed by the aquifer and reduce baseflow.

 

This past year, Whiteman’s Creek was already at dangerously low levels and since these 2 water features feed Whiteman’s Creek, reducing this flow will directly affect not only Whiteman’s Creek, but the Grand River itself. Considering the lack of precipitation this “winter”, we are in for a far worse summer this year. This should be considered. Since there is over 100 years of licenced extraction already (Gravelwatch) there is no need to proceed in a rush.

 

Rehabilitated Conditions Water Balance

 

There has not been 1 pit rehabilitated by an aggregate company in Paris. All of our pits remain wasteland except for those bought and rehabilitated by the public. Until the aggregate industry are forced to complete the rehabilitation of the existing sites around Brant, we will have to consider that this land will remain an unfinished gravel pit and that a new assessment be created assuming that the pit will remain in a similar state as the rest of the unfinished pits in the area. We have to live in reality here and acknowledge the past performance of aggregates in the area.

 

The citizens of Brant rehabilitated the Lefarge pit on Green Lane & spent $200,000 just for topsoil. According to TOARC, they spent a total of $310,000 to rehabilitate 38 pits. That is less than $20,000 a pit. Considering that they are sitting on $17 million and happy with the job they are doing, the rehabilitation program is then nothing more than an illusion. Considering the number of pits that have been abandoned in Brant, we must insist that the industry be forced to clean up the past pits to acceptable standards before proceeding with approving any new pits.

Perhaps a large security deposit on the land should be considered??

 

This property grows 3 crops of vegetables per year. This is highly productive farmland that should be protected.

 

Considering the remaining farmland, if there is found to be a chemical change in the water, what would the effects be on the crops down-gradient of the pit? What does increases in iron and manganese do to a crop? Will the county suddenly need to instal iron and manganese filters 10-20 years later due to iron and manganese increases at a cost of 10′s of millions?

 

A WHPA is less than 1 KM from this pit although there was not any mention of this in the study. Considering the changes that can occur to groundwater as a result of an aggregate operation, there should be assurances that this well will not be affected ANY time in the future. One potential change is an increase in iron and manganese that seems to occur in post extraction areas. This would require the installation of a costly filtration system that will be directly traceable back to the pit by the time it happens. Policy will also be that the company pays for these costs by the time that rolls around considering this official notice that that will be policy in the near future.

 

Air Quality study

 

Silica dust is known to be created in sand and gravel operations. You cannot deny it. Silica dust is a known carcinogen and cause of silicosis. This report does not mention any of this. Nearby residents will be subjected to this dust for at least 10 years. A study of the health of people living around an aggregate extraction to determine if there are higher levels of lung diseases should be carried out and used as proof before any consideration of opening this pit.

 

According to witnesses – people who live near pits now – they have to keep their windows closed 24/7 and their houses still fill with dust. One witness stated that they have to clean their TV screen every other day or they cannot see the picture. This is not a normal level of dust considering most people do not have to clean their screens.

 

The new Brant Business Park is located North-east of the pit. The very direction of prevailing winds. The taxpayers have invested over $7 million into this property and business that build there are investing much more. These companies will be faced with severe dust issues. BGI uses expensive printing equipment and high dust levels will cause many issues that will impair their operation. According to another witness, the dust does travel this far. All of these workers that populate these businesses will be subjected to increased levels of silica dust exposure for 8+ hours a day. The study neglects to address these issues.

 

This is advertised on the company’s information site:

 

What are the benefits to our community?

 

- Increased tax revenues paid directly to the County of Brant throughout the pit’s life (estimated to be about 10-20 years).

- St.Marys is also required to pay a fee per tonne extracted to the Ontario Aggregate Resources Corporation (TOARC). TOARC works on behalf of the Ministry of Natural Resources and a portion of the TOARC fees are directed to source municipalities.

 

The truth is, property taxes for a gravel pit are lower and the industry has even launched an action with MPAC all across Ontario to have their properties reassessed for the decrease in property value that they themselves caused for the entire area. This could result in taxpayers paying back previous revenues collected.

 

The industry has admitted that the tonnage fee is inadequate to cover the municipal cost at the ARA review & it is on record. The shortage has been documented and testified to actually cost the municipality over $800,000 per year.

 

These statements should not be allowed. The statements are deceiving and untrue.

 

The Traffic Impact Study concludes it’s executive summary (the only part 90% of the people ever read) by demanding that the taxpayer spend 100′s of thousands to build infrastructure to support the CBM pit: “North and southbound left turn lanes, a northbound right turn lane, and a northbound acceleration lane are recommended for the proposed pit access to Bishopsgate Road to accommodate site traffic demands. Since this recommendation falls outside the proposed license area, it is not enforceable under ARA. This recommendation is to be discussed further with the municipality in terms of geometric design requirements.”

 

So then is assumed to be covered by the taxpayer as demanded by Grant? It may not fall under the ARA but that still does not make it morally or ethically right. This just shows the arrogance of corporate entitlement to our tax dollars. My tax dollars are not to be used to support the aggregate industry.

 

This report lays out plans to upgrade the roads for the benefit of the operation and does not include any data on road damage caused by the trucks. It also does not consider school bus routes or anything regarding safety, noise or any community related concerns.

 

The report also heavily suggests the need for a new ramp at the 403 & Bishopsgate. Considering that the need will be driven by aggregate, this should be paid by the aggregate companies to support their infrastructure. It is very curious to see that the people who write these studies seem to be pushing to justify the need for even more development at the expense of the taxpayer and the benefit of themselves and the industry that they serve.

 

The County taxpayers already have enough of a tax burden and the ability for these corporations to freely dip into our pockets, even when we cannot afford it, has to stop now. There resources should benefit the people of the community, not enslave us to millions in debt to cover the costs associated to these operations. The 11 cent per tonne (probably rounded to 10 with the elimination of the penny) fee is immoral and should be $4-5 per tonne. This issue has to be resolved.

 

The public forums held by these companies are a complete waste of time. The companies tout them as a huge success despite the fact that the majority of community participants on these committees also lead the opposition groups. They never provide any proof to satisfy the community and there is absolutely no accountability for the actions or statements by these companies. If you say “trust the science” in the public then you better have that science that you are referring to. Accountability needs to be addressed.

 

I call to suspend all new licence applications until all of these issues are addressed.

 

These issues seriously need to be addressed. If the “experts” cannot (or will not) do it, I can put together protocols for scientific methodologies that would answer these questions. These same questions are being repeated by groups all over the province. Lets put the science together and find out the truth. It is the truth we are looking for is it not?

 

A Concerned Citizen Of Brant

 

* Notice that the above information has been gathered through private amateur research for the purpose of allowing the reader to make an informed and educated decision.  However, while the information is believed to be reliable, accuracy cannot be guaranteed. 

 

 

Return to AWARE-Ontario.ca Home Page

 

List of Ontario’s Issues

 

What Can I Do?